Skip to content
Qode Core

The facility

Capacity you cancontract now.

Existing, powered infrastructure in the UAE, being converted into AI capacity on a staged timeline. What remains is fit-out — scoped to your platform, not ours.

  • 5 MW

    Available today

    On an existing substation

  • 10–15 MW

    Expansion pathway

    Subject to utility approval

  • Tier III

    At launch

    Concurrently maintainable design

  • Tier IV

    Target, month six

    Fault-tolerant end state

The critical path

The long-lead itemsare already behind us.

A new AI data centre spends most of its timeline on things that are not compute. On this site, those are done.

Site & buildingsTypical:Land, design, permits, constructionComplete — 2 × 1,200 sqm high-standard buildings
Grid powerTypical:Utility application and connection, often the longest lead itemComplete — substation in place, 5 MW available
Power resilienceTypical:Procure and install generators, UPS / BESSIn place — backup generators and battery backup
Cooling plantTypical:Chiller procurement and installationIn place — AC, chillers and backup cooling
LicensingTypical:Entity setup and activity licensingInitial trade licence approval issued
GPU fit-out & commissioningTypical:After all of the aboveNext step — scoped to your platform and timeline

Investment goes into compute and commissioning, not concrete.

Why the critical path matters

A new AI data centre spends most of its timeline on things that are not compute: land, buildings, a grid connection, power resilience, a cooling plant, a licence. On this site, those are done. The table is the typical greenfield path against where this site stands today.

Render of a data-hall conversion: rack rows, with the Dubai skyline beyond the glazing
Render
Data-hall conversion — render

Infrastructure in place

Already built.Already powered.

Buildings, substation, cooling plant and standby power are on site. Direct liquid cooling is added at fit-out.

Facilities

Two 1,200 sqm warehouses built to a high standard, ready for data-hall conversion.

Power

Dedicated substation. 5 MW available, with a pathway to 10 MW and potentially 15 MW.

Cooling

AC and chillers in place with backup units. Direct liquid cooling is added at fit-out for high-density GPUs.

Standby generation

Backup generators providing on-site power resilience.

Battery / UPS

Battery backup for ride-through and clean transfer to generation.

Secure campus

A single-tenant-capable site with perimeter control for sovereign workloads.

Resilience programme

Tier III at launch.Tier IV by month six.

Both are targets. The design is built to them; the certificate is issued by the Uptime Institute, not by us.

Tier IIILaunch · target
Topology
N+1 power and cooling components; concurrently maintainable
Distribution
Dual-path delivery, one active path
Maintenance
Any component serviced without an IT outage
Certification
Uptime Institute Tier III Design & Constructed Facility — target
LaunchMonth 6
Tier IVMonth 6 · target
Topology
2N or 2(N+1) fault-tolerant power and cooling
Distribution
Dual active, compartmentalised paths
Fault tolerance
A single failure absorbed with no IT impact
Certification
Uptime Institute Tier IV Design & Constructed Facility — target
How contracted IT load is sized

A staged programme, so capacity goes live early without compromising the end state. Both certifications are targets: the design is built to them, and the certificate is issued by the Uptime Institute, not by us.

Under a 2N topology, contracted IT load is sized against redundant capacity. The IT megawatt allocation per phase is agreed with each partner.

Certification roadmap — targets

  • Uptime Tier III → IV
  • ISO/IEC 27001
  • ISO/IEC 27017 / 27018
  • ISO 22301
  • ISO 9001 / 14001 / 50001
  • SOC 1 & SOC 2 Type II
  • PCI DSS, as required
  • UAE IA Standard & PDPL

None of these is held today. Each is a target the facility and its operations are being built to, and each will be published with its certificate when it is issued.

Power & cooling · design targets

Engineered forBlackwell-class density.

Proposed design targets, confirmed against your reference architecture before anything is ordered.

Initial IT power
Up to 5 MW site capacity; IT allocation phased per partner
Expansion
10 MW, then up to 15 MW, subject to utility approval
Air-cooled racks
15–40 kW per rack — inference, RTX PRO 6000, CPU, storage
Liquid-cooled racks
40–80 kW per rack for HGX H100 / H200 / B200; 120–140 kW per rack for GB200 NVL72
Liquid cooling, heat rejection, PUE, monitoring
Liquid architecture
Direct-to-chip with in-row CDUs and a facility water loop; N+1, then 2N pumps
Heat rejection
Existing AC and chillers plus backup units; free-cooling hours where climate permits
PUE
Design target ≤ 1.3 at full liquid-cooled load
Monitoring
Real-time DCIM — per-rack power, inlet temperature, leak detection

Compute platforms · indicative

The GPU mixyou need.

Indicative support for current and next-generation NVIDIA platforms. The final mix is agreed with each partner.

Final mix

Agreed with each partner, against the workload.

  • Day 1

    RTX PRO 6000 Blackwell

    Inference, visual compute, enterprise AI

    Approx. power
    600 W / GPU
    Cooling
    Air
  • Day 1

    H100 (HGX 8-GPU)

    Training and inference, mature software stack

    Approx. power
    700 W / GPU
    Cooling
    Air or liquid
  • Day 1

    H200 (HGX 8-GPU)

    Large-model inference, memory-bound training

    Approx. power
    700 W / GPU
    Cooling
    Air or liquid
  • With DLC fit-out

    B200 (HGX 8-GPU)

    Frontier training, high-throughput inference

    Approx. power
    1,000 W / GPU
    Cooling
    Liquid preferred
  • With DLC fit-out

    GB200 NVL72

    Rack-scale training and reasoning inference

    Approx. power
    120–140 kW / rack
    Cooling
    Liquid required
  • Roadmap, 10–15 MW phase

    Next generation

    Blackwell Ultra and Rubin-class systems

    Approx. power
    Higher rack density
    Cooling
    Liquid
CPU nodes

CPU nodes (AMD EPYC, Intel Xeon or NVIDIA Grace) are sized to the partner's head-node and storage ratio.

Indicative support for current and next-generation NVIDIA platforms. The final mix is agreed with each partner; CPU nodes (AMD EPYC, Intel Xeon or NVIDIA Grace) are sized to the partner's head-node and storage ratio.

Network & interconnect · proposed

Non-blocking fabrics,to your reference design.

Proposed architecture. InfiniBand or Ethernet / RoCE is selected to the partner's standard.

  • Non-blocking

    1:1 subscription in the compute fabric

  • Low latency

    Sub-microsecond switch latency on InfiniBand

  • Validated

    NCCL all-reduce benchmarks at acceptance

  • Redundant

    Dual-homed spines and diverse fibre paths

The proposed architecture
External connectivity
Diverse carrier entries across multiple UAE carriers; private interconnect to the regional edge; DDoS protection
Front-end / storage
100–400 GbE Ethernet; high-performance parallel storage; tenant VRF segmentation
Compute fabric
NVIDIA Quantum-2 / X800 InfiniBand or Spectrum-X RoCE; 400–800 Gb/s per GPU; rail-optimised, non-blocking fat tree
In-node / in-rack
NVLink — 900 GB/s (Hopper) to 1.8 TB/s (Blackwell) per GPU; NVL72 as a single NVLink domain
Out-of-band
Isolated OOB network for BMC, PDUs and CDUs; jump-host access only

Acceptance & commissioning

Handed over onlywhen it is proven.

Five-level commissioning, then AI-specific cluster validation. Capacity is in service because it passed — not because it is installed.

  1. Step 1 · Factory & site

    L1–L3

    FAT witness, delivery inspection, component start-up checks

  2. Step 2 · Systems test

    L4

    Power, cooling and CDU functional tests, per system

  3. Step 3 · Integrated (IST)

    L5

    Full-load bank, utility-fail and failover scenarios

  4. Step 4 · GPU validation

    Burn-in

    72h+ stress, NVIDIA DCGM diagnostics, ECC and thermal

  5. Step 5 · Performance

    Cluster

    HPL, NCCL all-reduce, MLPerf training and inference

Proposed acceptance criteria
  • Benchmarks within an agreed tolerance of vendor reference results
  • Zero critical hardware faults during burn-in
  • Fabric bandwidth at line rate
  • Integrated systems test passed at full design load
  • Witnessed by partner engineers, with full test reports

Commercial models

Four waysto contract it.

The structure changes who owns the hardware and who runs it. The building, the power and the jurisdiction do not change.

  • Wholesale colocation

    Powered shell

    You deploy your own hardware into dedicated, powered and cooled halls.

    Per kW / month, committed

  • Reserved

    Dedicated GPU capacity

    Qode Core procures and operates GPUs to your specification, reserved exclusively for you.

    Per GPU-hour, take-or-pay

  • Bare metal

    Managed cluster

    A turnkey cluster with fabric, storage, monitoring and 24/7 operations.

    Per GPU-hour plus managed services

  • In-country

    Sovereign extension

    In-country capacity for your own sovereign and regulated customers in the UAE.

    Bespoke, multi-year

Term options of 3–5 years, with expansion rights over the 10–15 MW phases and a right of first refusal on new capacity.

Optional AI services on top — indicative
HZ AI orchestrationHigher utilisation; burst and surplus capacity monetised; one telemetry viewRevenue share per GPU-hour
Tynapse trust layerRegulated tenants deploy AI agents with real-time guardrails and audit evidencePer-workload subscription
QODE CortexFaster time to production for AI, GenAI, agentic and IoT workloads, on Lorgan's Enigma and ElliePlatform subscription + delivery
Arabic AI layerArabic-language models, retrieval and pages for Arabic-speaking usersManaged service
University AI HubA pipeline of new AI ventures and talent anchored in the UAECo-commercialisation per venture

Partnership roadmap

From agreementto Tier IV capacity.

Indicative, from a signed term sheet. The real dates depend on GPU lead times and on your specification.

  1. Months 0–3

    Design & procure

    • Joint requirements workshop
    • Reference architecture sign-off
    • GPU, network and DLC orders placed
    • Security and compliance gap review
  2. Months 3–6

    Tier III go-live

    • Fit-out and L1–L5 commissioning
    • GPU burn-in and cluster benchmarks
    • Partner acceptance and handover
    • First capacity in service
  3. Month 6

    Tier IV upgrade

    • 2N power and cooling paths live
    • Tier IV certification process
    • Commitments step up to Tier IV levels
    • Scale toward the full 5 MW
  4. Month 12+

    Expand

    • 10 MW phase activated
    • Next-generation GPU platforms
    • Pathway to 15 MW
    • Additional partner halls

Co-design

One workshop.Four decisions.

01

Capacity

Megawatts, phasing, rack density and the GPU platforms you need, from 5 MW toward 15 MW.

02

Model

Powered shell, dedicated GPU, managed cluster or sovereign extension — plus burst capacity.

03

AI services

Which layers to add: HZ AI orchestration, the Tynapse trust layer, QODE Cortex, Arabic AI.

04

Growth

University AI Hub ventures, internships, talent and regional go-to-market.

Co-design

Design yourcapacity blueprint.

Four decisions shape a Qode Core deployment. We work through them with you in one joint workshop, and leave it with phase one reserved.